PROJECT · TRANSPORT PLANNING
Kaduna Bus Rapid Transit
Junction concept design for the Kawo–Maraban Rido corridor — nineteen junctions redesigned around a centre-running median busway.

CLIENT
Kaduna State Transport Regulatory Authority
LOCATION
Kawo – Maraban Rido, Kaduna State
SCALE
24 km segregated corridor, 30 stations
STATUS
Stage 1 concept design, 2026
19
Junctions surveyed and redesigned
42,066
Vehicles a day at Katsina, the busiest junction
160,000
Passengers a day when the corridor opens
A bus lane is only as fast as the junctions it crosses.
Kaduna’s first bus rapid transit system runs 24 kilometres from Kawo in the north to Maraban Rido in the south, along Ali Akilu Road, Ahmadu Bello Way and Kachia Road, with 30 stations, a fleet of 120 articulated 18-metre buses and a design ridership of 160,000 passengers a day. It is financed by a €110 million facility from the French Development Agency and delivered by the Kaduna State Transport Regulatory Authority.
The buses run in the median, in their own carriageway, calling at far-side stations with a platform on each side. That one decision reaches every junction on the route. We surveyed nineteen of them over three days of classified turning-movement counts: Katsina is the busiest at 42,066 vehicles a day, Stadium at 39,809 and Naira at around 38,000.
Two roundabouts, Lugard and Stadium, are retained and signalised. Seven others are converted to signalised junctions outright. The corridor is set out to be built and opened in three phases rather than all at once.



Our role
Classified traffic surveys
Three-day classified turning-movement counts at all nineteen junctions on the corridor, establishing the demand each design has to carry.
Busway alignment and station layout
A centre-running median busway with dual-side-platform far-side stations, set out through each junction so buses hold priority along the whole route.
Junction concept design
Concept geometry for nineteen junctions — two roundabouts retained and signalised at Lugard and Stadium, seven converted to signalised junctions, the remainder redesigned in place.
Signal strategy
Phasing and coordination across the corridor, giving the busway priority without stalling the cross-town movements the city depends on.
Phasing and delivery plan
A three-phase delivery sequence so the corridor can be built and opened in usable sections.
Corridor length, station and fleet numbers, ridership and financing: Agence Française de Développement and the Kaduna State Transport Regulatory Authority. Junction count, survey basis, traffic volumes, junction treatments and phasing: Kaduna BRT Junction Concept Design Report, AEC Group Transport Planning & Highways, 10 July 2026 (Stage 1 Concept).
More work
See all projects
TRANSPORT PLANNING
Rehabilitation of BRT Lite Lanes: Mile 12 – CMS
Lagos State Government · 22 km

TRANSPORTATION & HIGHWAY
Trans-African Highway 7 — Lagos Section
Federal Ministry of Works · Seme – National Theatre

TRANSPORTATION & HIGHWAY
Rehabilitation of 500km of Rural Roads in Osun State
Osun State · RAAMP · 500 km
Have a project that has to work?
Tell us the constraint you cannot design around, and we will tell you how we would approach it.