The Proposed 4th Mainland Bridge

A 38-kilometre crossing from Ajah through Lekki and Baiyeku to Ikorodu — the largest single piece of transport infrastructure Lagos State has attempted.

Cloverleaf interchange from the air

CLIENT

Lagos State Government Office of Public-Private Partnerships

LOCATION

Ajah – Lekki – Ikorodu across the Lagos Lagoon

SCALE

38 km · 2 × 4 lane carriageway

STATUS

Preferred bidder appointed 2023

Lagos has three crossings between the mainland and the island. It needs a fourth.

The Fourth Mainland Bridge runs from Abraham Adesanya in Ajah, through Langbasa in Lekki and Baiyeku, across the Lagos Lagoon to Itamaga in Ikorodu. Procured by Lagos State through its Office of Public-Private Partnerships, it has been valued at around US$2.5 billion.

A crossing of this length is not really a bridge problem. It is a question of what the corridor does to land use, to demand on the existing three bridges, and to the economics of every journey it shortens.

Elevated link road over a canal

Our role

01

Corridor and demand assessment

Modelling the diversion effect on the Third Mainland, Carter and Eko bridges, and the induced demand the new corridor generates on both shores.

02

Route and interchange appraisal

Comparative assessment of alignment options across the lagoon, and interchange arrangements at Ajah, Langbasa and Itamaga.

03

Geotechnical and marine assessment

Ground and lagoon-bed conditions along the alignment, and their implications for foundation type and cost.

04

Economic and PPP appraisal

Whole-life cost, toll revenue sensitivity and the structuring questions a concession of this size has to answer.